Live courthouse data across 10 states. Pro users get alerted instantly on every filing. Get started

State ex rel. Boggs v. Cleveland

Docket 112111

Court of record · Indexed in NoticeRegistry archive · AI-enriched for research

CivilAffirmed
Filed
Jurisdiction
Ohio
Court
Ohio Court of Appeals
Type
Opinion
Case type
Civil
Disposition
Affirmed
Judge
Boyle
Citation
2026-Ohio-1450
Docket
112111

Appeal from summary judgment in a mandamus action alleging inverse condemnation following remand from federal court

Summary

The Eighth District Court of Appeals, on remand from the Ohio Supreme Court, affirmed the trial court’s ruling that relators’ writ of mandamus alleging inverse condemnation against the City of Cleveland was not barred by the four-year statute of limitations. The court concluded the cause of action did not accrue until the airport runway expansion at issue was completed in August 2004, because that completion was when all events fixing Cleveland’s alleged liability occurred. Because the relators filed their mandamus petition on August 1, 2008, the court held the action was timely and remanded the case for further proceedings on the merits of the taking claim.

Issues Decided

  • Whether the four-year statute of limitations in R.C. 2305.09(E) bars relators’ mandamus action alleging a physical taking by a foreign municipality.
  • When the cause of action for an alleged taking by a municipality accrues for statute-of-limitations purposes — at notice of proposed project, a demand to purchase, or completion of the project.

Court's Reasoning

The court applied Ohio precedent holding that a cause of action accrues when all events that fix the government’s alleged liability have occurred and the plaintiff knew or should have known of them. Here the runway expansion was not completed until August 2004, and the court found completion was the event that fixed the city’s liability. Because the mandamus petition was filed on August 1, 2008 — within four years of completion — the claim was timely.

Authorities Cited

  • R.C. 2305.09(E)
  • State ex rel. Doner v. Zody2011-Ohio-6117
  • State ex rel. Nickoli v. Erie MetroParks2010-Ohio-920

Parties

Petitioner
Susan Boggs (State ex rel.)
Petitioner
Fouad Rachid
Petitioner
Fouad, Inc.
Respondent
City of Cleveland
Judge
Mary J. Boyle
Judge
Michelle J. Sheehan
Judge
Lisa B. Forbes

Key Dates

Property acquisition by Fouad, Inc.
1995-07-11
Construction begins on runway one
2001-01-01
Runway one initial opening (Stage 1)
2002-12-01
Runway one completed (Stage 2)
2004-08-01
Construction begins on runway two extension
2007-05-01
Mandamus action filed in trial court
2008-08-01
Runway two opens
2008-12-01
Opinion released (this court)
2026-04-23

What You Should Do Next

  1. 1

    Proceed to trial court on the takings claim

    The relators should continue pursuing the mandamus action in the trial court to prove that the city’s actions amounted to a compensable taking and to seek appropriation proceedings or compensation.

  2. 2

    Prepare merits discovery and evidence

    Both parties should assemble and exchange evidence on noise, vibration, property devaluation, project timelines, and causation to address whether a cognizable taking occurred.

  3. 3

    Consult counsel about appellate options

    Either party should consult their attorney about preserving issues for appeal and whether further review to the Ohio Supreme Court is appropriate after the trial-court proceedings conclude.

Frequently Asked Questions

What did the court decide?
The appeals court held the property owner’s mandamus claim was filed within the four-year statute of limitations because the cause of action accrued when the runway expansion was completed in August 2004, so the 2008 filing was timely.
Who is affected by this decision?
The relators (Boggs, Rachid, and Fouad, Inc.) may proceed with their mandamus claim against the City of Cleveland; the city remains defendant and must defend on the merits.
What happens next in the case?
The case is remanded to the trial court for further proceedings consistent with this opinion and the Ohio Supreme Court’s prior remand, including adjudication of whether Cleveland’s actions amounted to a compensable taking.
Why wasn’t the claim time-barred based on earlier notice of the project?
The court found the government’s liability was not fixed until the runway expansion was completed, so earlier notices or demands did not start the four-year limit.
Can this decision be appealed again?
Possibly; parties may seek further review to the Ohio Supreme Court if jurisdictional criteria are met, though this decision follows the Supreme Court’s remand instructions.

The above suggestions and answers are AI-generated for informational purposes only. They may contain errors. NoticeRegistry assumes no responsibility for their accuracy. Consult a qualified attorney before relying on them.

Full Filing Text
[Cite as State ex rel. Boggs v. Cleveland, 2026-Ohio-1450.]




                               COURT OF APPEALS OF OHIO

                              EIGHTH APPELLATE DISTRICT
                                 COUNTY OF CUYAHOGA

SUSAN BOGGS, STATE EX REL.,
ET AL.,                                                 :

                 Relators-Appellants /
                 Cross-Appellees,                       :
                                                              No. 112111
                 v.                                     :

CITY OF CLEVELAND,                                      :

                 Respondent-Appellee /
                 Cross-Appellant.                       :


                                JOURNAL ENTRY AND OPINION

                 JUDGMENT: AFFIRMED; REMANDED
                 RELEASED AND JOURNALIZED: April 23, 2026


             Civil Appeal from the Cuyahoga County Court of Common Pleas
                                 Case No. CV-08-666718


                                             Appearances:

                 The Lindner Law Firm, LLC, and Daniel F. Lindner, for
                 appellants / cross-appellees.

                 Mark Griffin, Cleveland Director of Law; Elena N. Boop,
                 Chief Trial Counsel; James R. Russell, Jr., Chief Assistant
                 Director of Law; and Gilbert E. Blomgren, Assistant
                 Director of Law, for appellee / cross-appellant.
MARY J. BOYLE, J.:

              This case is before this court on remand from the Ohio Supreme

Court in State ex rel. Boggs v. Cleveland, 2025-Ohio-5094 (“Boggs II”), for further

review of our decision in State ex rel. Boggs v. Cleveland, 2023-Ohio-3871 (8th

Dist.) (“Boggs I”). The Ohio Supreme Court has reversed and remanded the matter

to this court for consideration of the cross-assignment of error raised by

respondent-appellee / cross-appellant, the City of Cleveland (“Cleveland”)

asserting that the statute of limitations bars relators-appellants / cross-appellees,

Susan Boggs (“Boggs”), Fouad Rachid (“Rachid”), and Fouad Inc.’s (collectively,

“Boggs”) writ of mandamus alleging claims for inverse condemnation. For the

reasons set forth below, we affirm the trial court’s finding that Boggs’s claims are

not barred by the statute of limitations. Consequently, this case is remanded to the

trial court for proceedings consistent with this opinion and Boggs II.

I. Facts and Procedural History

              The following is a summary of the facts and procedural history:

      [Boggs] and [Rachid] live in a home owned by Fouad, Inc.
      ([collectively, “Boggs”]). The home is located on the edge of Olmsted
      Township, near the Cleveland-Hopkins International Airport [airport].
      Boggs claims that low overhead flights and other airport operations
      have interfered with her use and enjoyment of her home to such an
      extent that it has amounted to a taking of the property. . . . Boggs
      instituted a mandamus action against the owner of the airport, the City
      of Cleveland, seeking to compel the institution of appropriation
      proceedings.

      ...

      Fouad, Inc., has owned the Olmsted Township home where Boggs and
      Rachid live since 1995. The airport, which is located entirely in
Cleveland, has been in operation since 1925. In 1999, Cleveland began
a project to expand two runways. As part of the expansion, the Federal
Aviation Administration (“FAA”) required Cleveland to fund sound-
dampening measures for neighboring properties that would be affected
by the expansion, including Boggs’s property. See Boggs v. Cleveland,
FAA-2016-9337, 2017 FAA LEXIS 253, 2017 WL 11438604, *2 (Jan. 24,
2017). And though the FAA did not require Cleveland to purchase any
of the properties, see id., Cleveland obtained “avigation easements” (air
easements) from various landowners in Olmsted Township. Boggs
declined Cleveland’s offer to purchase an easement.

According to Boggs, the runway-expansion project caused increased air
traffic over her home that interferes with her ability to live in her home.
Specifically, she claims that the flights cause noise and vibrations and
emit fuel and debris onto her property. Boggs testified that she no
longer wants to live there and cannot profit from a sale because the
noise and shaking caused by low-flying air traffic have made it
unsuitable for residential use.

Boggs instituted the lawsuit that is the subject of this appeal in 2008,
after Cleveland began work on expansion of the second runway. She
sought relief in mandamus, alleging that Cleveland’s operation of the
airport constituted a taking under the Fifth Amendment to the United
States Constitution and “other applicable laws.” Cleveland removed
the case to federal court. In federal court, the parties agreed to a
dismissal without prejudice and a tolling of the statute of limitations to
allow Boggs to pursue administrative remedies with the FAA. The FAA
rejected Boggs’s claim that Cleveland violated its grant assurances by
extending the airport’s runways in such a manner as to place Boggs’s
home within the “landing area” of the airport. Boggs v. Fed. Aviation
Admin., 764 Fed.Appx. 480, 483 (6th Cir. 2019). The Sixth Circuit
affirmed, concluding that Boggs’s property was not part of the landing
area because “the statutory definition of landing area describes an area
of land and water, not air.” Id. at 485.

After Boggs was unsuccessful at the FAA, proceedings resumed in
federal court in 2019. Ultimately, the district court granted summary
judgment in Cleveland’s favor on Boggs’s federal takings claim. Boggs
v. Cleveland, 2021 U.S. Dist. LEXIS 101308, 2021 WL 2188794, *1
(N.D.Ohio May 28, 2021). The district court declined to exercise
supplemental jurisdiction over Boggs’s state-law claims and remanded
the case to the common pleas court. Id.
      Following remand, the state-court proceedings picked up in July 2021.
      Both parties moved for summary judgment. Boggs argued that the
      evidence demonstrated that she was entitled to a writ of mandamus
      compelling Cleveland to initiate appropriation proceedings. Cleveland
      argued that Boggs lacked standing to pursue the mandamus action,
      that the claim was barred by the statute of limitations, and that Boggs
      had failed to establish a taking of her property.

Boggs II at ¶ 2, 6-10.

               Although the airport had several expansions and modifications since

1925, at issue in the case was “the expansion of runways labelled 6L-24R [‘runway

one’] and 6R-24L [‘runway two’]. Runways [one] and [two] run parallel to each

other. They lie on a diagonal in the northeast and southwest direction. The Airport

boundary, where the runways terminate, lies across the road from [Rocky River]

Reservation.” Boggs I, 2023-Ohio-3871, ¶ 6. According to Boggs I, the parties

stipulated, at the trial-court level, to the following timeline regarding the expansion

of the runways:

      • July 11, 1995: Fouad Inc. acquires the [Boggs’s] Property;

      • January 2001: Construction begins on new runway [one];

      • December 2002: Runway [one] opens at an initial length of 7,000 feet
      (Stage 1);

      • January 2003: Construction restarts on runway [one];

      • August 2004: Runway [one] opens at a final length of 9,000 feet
      (Stage 2);

      • May 2007: Construction begins on runway [two] extension;

      • August 1, 2008: [Boggs] file the instant action against [Cleveland];

      • December 2008: Runway [two] opens at a final length of 9,956 feet[.]
Boggs I at ¶ 6.

      The trial court granted summary judgment in Cleveland’s favor.
      Cuyahoga C.P. No. CV-08-666718, 2022 WL 21713279, *9 (Nov. 1,
      2022). Although the trial court rejected Cleveland’s claim that the
      action was barred by the statute of limitations, it concluded that Boggs
      had failed to establish standing. Id. at *7, 9. The court reasoned that a
      municipality lacks authority to appropriate property outside its
      boundaries absent specific statutory authorization. Id. at *9. Because
      it determined that no statute authorized Cleveland to appropriate
      Boggs’s property, the trial court held that Boggs’s lawsuit was not
      redressable by a writ of mandamus. Id.

      The court of appeals affirmed the trial court’s decision that Boggs
      lacked standing to pursue her mandamus action. [Boggs I,] 2023-
      Ohio-3871, ¶ 46 (8th Dist.). It noted that mandamus is the appropriate
      remedy to compel a public authority to institute an appropriation
      action when there has been an involuntary taking of public property.
      Id. at ¶ 22. But it concluded that Boggs did not have standing to pursue
      such an action against Cleveland. Id. at ¶ 23. One element of standing,
      the court explained, is that a litigant’s injury is “likely to be redressed
      by the requested relief.” Id., citing Moore v. Middletown, 133 Ohio St.
      3d 55, 2012-Ohio-3897, ¶ 22, 975 N.E.2d 977, and Lujan v. Defenders
      of Wildlife, 504 U.S. 555, 560-561, 112 S. Ct. 2130, 119 L. Ed. 2d 351
      (1992). This element, the court concluded, was not met because
      Cleveland did not have the authority to appropriate Boggs’s property.
      Id. at ¶ 33, 43.

      In reaching this conclusion, the court first rejected the notion that
      Boggs had standing by virtue of the guarantee of “compensation” when
      private property is taken for public use in Article I, Section 19 of the
      Ohio Constitution. Id. at ¶ 26. It opined that Article I, Section 19 was
      “limited by” Ohio’s home-rule provision, Article XVIII, Section 3 of the
      Ohio Constitution. Id. at ¶ 27. Under the home-rule provision, the
      court explained, a municipality has no authority to take property
      outside its city limits aside from acquiring property for a public utility
      to serve its own residents. Id. And the court concluded that because a
      municipality lacks constitutional authority to appropriate property
      beyond its boundaries, a property owner cannot pursue a mandamus
      claim to force a city to commence appropriation proceedings for the
      purpose of providing compensation for a taking that has occurred. Id.
      at ¶ 28, 35. It premised this conclusion on two opinions, Clifton v.
      Blanchester, 2012-Ohio-780, 131 Ohio St. 3d 287, 964 N.E.2d 414, and
      Moore, in which this court held that a property owner lacked standing
      to pursue a mandamus action for a regulatory-takings claim against a
      foreign municipality. See id. at ¶ 28.

      The court of appeals also considered whether any statute authorized
      Cleveland to appropriate Boggs’s property. It noted that R.C. 719.01
      authorized a municipality to appropriate property for purposes of
      establishing “airports” and “landing fields.” Id. at ¶ 38. But it
      determined that Boggs’ property did not fall within the statutory
      definitions of these terms set forth in R.C. 4561.01. Id. at ¶ 42, citing
      R.C. 4561.01. It explained that “the definitions of ‘airport’ and ‘landing
      field’ are specifically limited to ‘any location either on land or water’”
      and therefore did not authorize Cleveland to take property beyond the
      physical boundaries of the airport. Id., quoting R.C. 4561.01(C) and
      (D). Thus, because neither the Ohio Constitution nor any statute
      authorized Cleveland to appropriate Boggs’s property, the court of
      appeals held that Boggs lacked standing to pursue a mandamus action.
      Id. at ¶ 44.

      In the court of appeals, Cleveland also sought to defend the trial court’s
      judgment on the alternative basis that Boggs’s claim was barred by the
      statute of limitations. See App. R. 3(C)(2) (allowing an appellee “to
      defend an order appealed by an appellant on a ground other than that
      relied on by the trial court”). But because the court of appeals
      determined that Boggs lacked standing, it did not reach the statute-of-
      limitations issue. [Boggs I,] 2023-Ohio-3871 at ¶ 45 (8th Dist.).

Boggs II at ¶ 11-15.

               The Supreme Court accepted Boggs’s appeal on two propositions of

law. In the first proposition of law, Boggs argued that she had standing because

R.C. 719.01 allows a municipality to acquire property outside its jurisdiction for the

purpose of constructing an airport. In the second, Boggs challenged this court’s

conclusion that Article I, Section 19 is an insufficient basis for standing, arguing that

Clifton and Moore should not be read to bar a physical-takings claim against a

foreign municipality.
              The Ohio Supreme Court agreed with Boggs and declined to “extend

Clifton and Moore beyond their ‘unique facts.’” Boggs II at ¶ 52. In addition, the

Court held that “a person who alleges that his property has been taken by a foreign

municipality may pursue a mandamus action to force the municipality to institute

appropriation proceedings for purposes of compensating the landowner for

property that has been taken.” Id. In other words, the Court held that Boggs has

standing to pursue her mandamus claim. Id. Accordingly, the Ohio Supreme Court

reversed this court’s decision in Boggs I and remanded the matter for this court to

consider Cleveland’s statute-of-limitations argument, which states:

      Cross-Assignment of Error: The trial court’s judgment in favor of
      [Cleveland] should be affirmed because the applicable statute of
      limitation bars the remaining claim against it.

II. Law and Analysis

              In the cross-appeal, Cleveland asserts that the trial court erred when

it held that Boggs’s claims are not barred by the four-year statute of limitations. We

find no merit to Cleveland’s argument.

              An appellate court reviews the grant or denial of summary judgment

de novo. Grafton v. Ohio Edison Co., 77 Ohio St.3d 102, 105 (1996). In a de novo

review, the appellate court affords no deference to the trial court’s decision and

independently reviews the record to determine whether summary judgment is

appropriate. Hollins v. Shaffer, 2009-Ohio-2136, ¶ 12 (8th Dist.); Smathers v.

Glass, 2022-Ohio-4595, ¶ 30. Summary judgment is appropriate if (1) no genuine

issue of any material fact remains; (2) the moving party is entitled to judgment as a
matter of law; and (3) it appears from the evidence that reasonable minds can come

to but one conclusion and, construing the evidence most strongly in favor of the

nonmoving party, that conclusion is adverse to the nonmoving party. Grafton at

105.

               The party moving for summary judgment bears the burden of

demonstrating that no genuine issues of material fact exist for trial. Dresher v. Burt,

75 Ohio St.3d 280, 292-293 (1996). The moving party has the initial responsibility

of informing the trial court of the basis for the motion and identifying those portions

of the record that demonstrate the absence of a genuine issue of material fact on the

essential elements of the nonmoving party’s claims. Id. “To accomplish this, the

movant must be able to point to the evidentiary materials of the type listed in

Civ.R. 56(C) that a court is to consider in rendering summary judgment.” Id. These

include “the pleadings, depositions, answers to interrogatories, written admissions,

affidavits, transcripts of evidence, and written stipulations of fact, if any.”

Civ.R. 56(C). “These evidentiary materials must show that there is no genuine issue

as to any material fact, and that the moving party is entitled to judgment as a matter

of law.” Dresher at 293.

               After the moving party has satisfied this initial burden, the

nonmoving party has a reciprocal duty to set forth specific facts by the means listed

in Civ.R. 56(C) showing that there is a genuine issue of material fact. Id. “One of

the principal purposes of the summary judgment rule is to isolate and dispose of

factually unsupported claims or defenses.” Am. Dental Ctr. v. Wunderle, 1993 Ohio
App. LEXIS 4437, *4 (8th Dist. Sept. 16, 1993), citing Celotex Corp. v. Catrett, 477

U.S. 317, 323-324 (1986). This court has explained:

      “[T]he plain language of the summary judgment rule mandates the
      entry of summary judgment, after adequate time for discovery, and
      upon motion, against a party who fails to make a showing sufficient to
      establish the existence of an element essential to that party’s case, and
      on which that party will bear the burden of proof at trial. In such a
      situation, there can be no ‘genuine issue as to any material fact,’ since
      a complete failure of proof concerning an essential element of a non-
      moving party’s case necessarily renders all other facts immaterial.”

(Citations omitted.) Corradi v. Soclof, 1995 Ohio App. LEXIS 2162, *6 (8th Dist.

May 25, 1995), quoting Toensing v. MK-Ferguson Co., 76 Ohio App.3d 826, 830

(8th Dist. 1992), citing Celotex Corp. at 323-324.

               Thus, we independently review Cleveland’s motion for summary

judgment to determine whether Boggs’s writ of mandamus action filed on August 1,

2008, is barred by the statute of limitations.

               Initially we note that the parties agree that a four-year statute of

limitations as set forth in R.C. 2305.09(E) applies, which establishes that an action

for relief on “the grounds of a physical or regulatory taking of real property” must be

brought within four years after the cause of action accrues. In State ex rel. Nickoli

v. Erie MetroParks, 2010-Ohio-920, and reaffirmed in State ex rel. Doner v. Zody,

2011-Ohio-6117, ¶ 34, the Ohio Supreme Court held that a “‘cause of action against

the government has “first accrued” only when all the events which fix the

government’s alleged liability have occurred and the plaintiff was or should have

been aware of their existence.’” Nickoli at ¶ 34, quoting Hopland Band of Pomo
Indians v. United States, 855 F.2d 1573, 1577 (Fed.Cir. 1988). Likewise, this court

has held that “[a] cause of action for injury to real property and relief on the grounds

of a physical or regulatory taking accrues, and the four-year statute of limitation

commences to run, when the injury or taking is first discovered, or through the

exercise of reasonable diligence, should have been discovered.”           State ex rel.

Stamper v. Richmond Hts., 2010-Ohio-3884, ¶ 25 (8th Dist.). This applies to

actions, such as this one, for mandamus relief to begin appropriation proceedings.

Zody at paragraph four of the syllabus (Mandamus is the appropriate action to

compel public authorities to institute appropriation proceedings when an

involuntary taking of private property is alleged.). Therefore, the question before

this court is when did the cause of action accrue.

               Cleveland asserts that the trial court erred in its application of the

four-year statute of limitations because Boggs’s claims accrued at the latest in 2002.

Cleveland maintains that Boggs was aware of the potential for mandamus relief as

early January 2001, when Boggs was notified of the proposed expansion of the

runways, or at the latest August 7, 2002, when Boggs made a formal demand that

Cleveland purchase the property. Cleveland claims that this is when the injury or

taking was first discovered or through reasonable diligence, should have been

discovered. Because the cause of action was filed on August 1, 2008, Cleveland

argues that it is time-barred.

               Whereas Boggs asserts that the suit was timely filed because it was

filed within four years of the completion of runway one in August 2004. Boggs
argues that runway one was enlarged to a length of 7,000 feet in 2002 and then

expanded again in 2004 to a total of 9,000 feet, which is 2,000 feet closer to Boggs’s

property. Boggs argues that any petition arguing the effects of the 2004 expansion

of runway one would not have been ripe until its completion in August 2004.

              After careful review of the record, we are not persuaded by

Cleveland’s argument that the mandamus action accrued at the latest in 2002,

because it is undisputed that the expansion of runway one was not completed until

August 2004. We find that the completion of runway one is when all the events that

fix the government’s alleged liability occurred. Therefore, the filing of Boggs’s writ

of mandamus on August 1, 2008, was within the four-year-statute of limitations.

              In light of the foregoing, we find that the trial court did not err by

holding that Boggs’s claims are not barred by the statute of limitations.

              Accordingly, Cleveland’s cross-assignment of error is overruled.

              Judgment affirmed; cause remanded. This case is remanded to the

trial court for proceedings consistent with this opinion and Boggs II. We note that

“[t]0 be successful, Boggs will need to show that Cleveland’s actions amounted to a

cognizable taking of her property.” Boggs II at ¶ 55.

      It is ordered that appellants / cross-appellees recover from appellee / cross-

appellant costs herein taxed.

      The court finds there were reasonable grounds for this appeal.

      It is ordered that a special mandate be sent to said court to carry this judgment

into execution.
      A certified copy of this entry shall constitute the mandate pursuant to Rule 27

of the Rules of Appellate Procedure.


___________________________
MARY J. BOYLE, JUDGE

MICHELLE J. SHEEHAN, A.J., and
LISA B. FORBES, J., CONCUR