Xcel Energy subsidiary Southwestern Public Service Company filed with the Texas Public Utility Commission on March 3, 2026 to recover transmission capital costs and federal wholesale transmission charges incurred from Jan 1, 2023 through Dec 31, 2025 via a Transmission Cost Recovery Factor (TCRF).
Key Takeaways
- Filing date: March 3, 2026
- Seeking recovery of transmission costs from 2023–2025
- Requesting a Transmission Cost Recovery Factor (TCRF)
- Costs include capital investments and approved wholesale charges
Research context
What to do next
- 1
Review the full PUC filing
Obtain SPS's complete application and exhibits from the Public Utility Commission of Texas docket filed March 3, 2026 for specifics on requested amounts.
- 2
Monitor PUC docket and deadlines
Watch the PUC docket for protest, intervention, or comment deadlines and for hearing dates issued by the Commission.
Frequently asked questions
- What is a TCRF and why did SPS file for it?
- A TCRF is a mechanism to recover transmission capital and approved wholesale transmission costs; SPS filed to recover costs from Jan 1, 2023–Dec 31, 2025.
- When was the filing made with the Public Utility Commission of Texas?
- The filing was made on March 3, 2026.
- Who reviews and approves this TCRF request?
- The Public Utility Commission of Texas reviews the application under PURA §36.209 and 16 Tex. Admin. Code §25.239.
The suggestions and answers above are AI-generated for general information only. They can be wrong, and we don't take responsibility for their accuracy. Talk to a qualified professional before acting on them.
Legal terms in this notice
- Transmission Cost Recovery Factor (TCRF)
- A rider that lets a utility recover approved transmission capital and wholesale transmission costs outside base rates.
- Test year
- The period used in a previous rate case to measure costs and set base rates.
Full Notice Text
SOUTHWESTERN PUBLIC SERVICE COMPANY NOTICE OF RATE CHANGE REQUEST Southwestern Public Service Company (SPS), doing business as Xcel Energy, filed a statement of intent and application with the Public Utility Commission of Texas (Commission) for approval of a Transmission Cost Recovery Factor (TCRF) on March 3, 2026. The filing was made in accordance with the Public Utility Regulatory Act Section 36.209 and 16 Tex. Admin. Code Section 25.239. A TCRF allows a utility to recover its reasonable and necessary costs for transmission capital costs and wholesale transmission charges approved by a federal regulatory authority incurred since the end of the test year in the utility's last base rate case. In this application, SPS is seeking recovery of costs for transmission capital investments it incurred from January 1, 2023 through December 31, 2025. SPS also seeks to recover approved transmission charges that are not otherwise being recovered through base rates. SPS requests that the