Case #CP26-241-000
Public Notice Case Dossier · AI-powered analysis
- Filings
- 2
- First filed
- May 7, 2026
- Last updated
- May 7, 2026
- State
- Iowa
Sign up and upgrade to Pro to download the full Case Dossier PDF
Get an AI-written analysis of this case's progression, current status, and key events.
Upgrade to ProWatch this case
Get alerted when new notices are filed for case CP26-241-000.
Filing Timeline
Northern Natural Gas seeks FERC approval to build a 2.48-mile pipeline extension, uprate 6.83 miles of existing line, and modify compressor stations for service beginning November 1, 2027. Landowner easements and construction in 2027 are planned to meet contractual winter service obligations.
View noticeNorthern Natural Gas filed with FERC to build a 2.48-mile extension and uprate 6.83 miles of its Des Moines C-line plus compressor modifications, aiming for service by November 1, 2027. Landowner easements and federal approval are required before construction in 2027.
View notice