Public Hearing — Des Moines (CP26-241-000)
Official courthouse record · Indexed in NoticeRegistry archive · AI-enriched for research
Northern Natural Gas seeks FERC approval to build a 2.48-mile pipeline extension, uprate 6.83 miles of existing line, and modify compressor stations for service beginning November 1, 2027. Landowner easements and construction in 2027 are planned to meet contractual winter service obligations.
Key Takeaways
- FERC docket CP26-241-000 filed April 17, 2026
- 2.48-mile pipeline extension and 6.83-mile uprate proposed
- Construction planned in 2027 for Nov 1, 2027 service start
- Landowners will be contacted about temporary and permanent easements
- Aboveground valve and appurtenant facilities included